The construction of the track begins on May 16th, to be completed by July 20th.
Project Architect: Mark Wrona of URS, Grand Rapids
General Contractor: Parrish Excavating, Quincy, MI
Cost: $637,456.00
Project Highlights
- New sub base, asphalt, running surface (polyurethane)
- New high jump area
- New long jump and pole vault area
- Many drainage issues addressed, both around track and football field
- New walkways to home and visitors bleachers, and concession stand
- New concrete plaza around concession area
- New irrigation system for football field
- Erosion and weed control under bleachers
-
New 4’ fence around perimeter of track